11/16/2017 FINAL Update
Highlighted in red are the final updates to the project. Thank you for your patience as we completed this conversion project.
Phase |
Boring - Start Date |
Boring - Estimated Completion |
Conversion - Start Date |
Conversion - Estimated Completion |
1 |
Not Applicable |
Not Applicable |
7/20/2017 |
COMPLETED |
2 |
7/31/2017 |
8/4/2017 |
8/15/2017 |
COMPLETED |
3 |
7/24/2017 |
7/28/2017 |
8/2/2017 |
COMPLETED |
4 |
Not Applicable |
Not Applicable |
8/7/2017 |
COMPLETED |
5 |
Not Applicable |
Not Applicable |
8/28/2017 |
COMPLETED |
6 |
Not Applicable |
Not Applicable |
8/8/2017 |
COMPLETED |
7 |
Not Applicable |
Not Applicable |
8/28/2017 |
COMPLETED |
8 |
7/17/2017 |
7/21/2017 |
7/26/2017 |
COMPLETED |
8/28/2017 Update
Highlighted in red are updates to the project schedule.
Phase |
Boring - Start Date |
Boring - Estimated Completion |
Conversion - Start Date |
Conversion - Estimated Completion |
1 |
Not Applicable |
Not Applicable |
7/20/2017 |
COMPLETED |
2 |
7/31/2017 |
8/4/2017 |
8/15/2017 |
COMPLETED |
3 |
7/24/2017 |
7/28/2017 |
8/2/2017 |
COMPLETED |
4 |
Not Applicable |
Not Applicable |
8/7/2017 |
COMPLETED |
5 |
Not Applicable |
Not Applicable |
8/28/2017 |
9/5/2017 |
6 |
Not Applicable |
Not Applicable |
8/8/2017 |
9/8/2017 |
7 |
Not Applicable |
Not Applicable |
8/28/2017 |
9/11/2017 |
8 |
7/17/2017 |
7/21/2017 |
7/26/2017 |
COMPLETED |
To view the map for phases 1-7, click here.
To view the map for phase 8, click here.
8/14/2017 UPDATE:
Highlighted in red are updates to the project schedule.
Phase |
Boring - Start Date |
Boring - Estimated Completion |
Conversion - Start Date |
Conversion - Estimated Completion |
1 |
Not Applicable |
Not Applicable |
7/20/2017 |
COMPLETED |
2 |
7/31/2017 |
8/4/2017 |
8/15/2017 |
8/21/2017 |
3 |
7/24/2017 |
7/28/2017 |
8/2/2017 |
COMPLETED |
4 |
Not Applicable |
Not Applicable |
8/7/2017 |
COMPLETED |
5 |
Not Applicable |
Not Applicable |
8/21/2017 |
8/28/2017 |
6 |
Not Applicable |
Not Applicable |
8/8/2017 |
8/23/2017 |
7 |
Not Applicable |
Not Applicable |
8/28/2017 |
9/11/2017 |
8 |
7/17/2017 |
7/21/2017 |
7/26/2017 |
COMPLETED |
8/1/2017 UPDATE:
Highlighted in red are updates to the project schedule.
Phase |
Boring - Start Date |
Boring - Estimated Completion |
Conversion - Start Date |
Conversion - Estimated Completion |
1 |
Not Applicable |
Not Applicable |
7/20/2017 |
COMPLETED |
2 |
7/31/2017 |
8/4/2017 |
8/15/2017 |
8/21/2017 |
3 |
7/24/2017 |
7/28/2017 |
8/2/2017 |
8/4/2017 |
4 |
Not Applicable |
Not Applicable |
8/7/2017 |
8/8/2017 |
5 |
Not Applicable |
Not Applicable |
8/9/2017 |
8/9/2017 |
6 |
Not Applicable |
Not Applicable |
8/22/2017 |
8/28/2017 |
7 |
Not Applicable |
Not Applicable |
8/10/2017 |
8/14/2017 |
8 |
7/17/2017 |
7/21/2017 |
7/26/2017 |
COMPLETED |
7/25/2017 UPDATE:
Highlighted in red are updates to the project schedule.
Phase |
Boring - Start Date |
Boring - Estimated Completion |
Conversion - Start Date |
Conversion - Estimated Completion |
1 |
Not Applicable |
Not Applicable |
7/20/2017 |
COMPLETED |
2 |
7/31/2017 |
8/4/2017 |
8/15/2017 |
8/21/2017 |
3 |
7/24/2017 |
7/28/2017 |
8/3/2017 |
8/4/2017 |
4 |
Not Applicable |
Not Applicable |
8/7/2017 |
8/8/2017 |
5 |
Not Applicable |
Not Applicable |
8/9/2017 |
8/9/2017 |
6 |
Not Applicable |
Not Applicable |
8/22/2017 |
8/28/2017 |
7 |
Not Applicable |
Not Applicable |
8/10/2017 |
8/14/2017 |
8 |
7/17/2017 |
7/21/2017 |
7/26/2017 |
8/2/2017 |
Earlier this year, Traverse City Light & Power (TCL&P) approved a meter exchange with Cherryland Electric Cooperative (Cherryland) to transfer customer electric service from Cherryland over to TCL&P and vice versa. The exchange offered redundancy and increased reliability for both TCL&P and Cherryland customers.
To assist customers impacted by this meter exchange, TCL&P has created maps outlining the location of Cherryland customers who will soon be transferred over to TCL&P service.
To view the map for phases 1-7, click here.
To view the map for phase 8, click here.
Going forward, TCL&P will provide updates via our website and Facebook Page that will outline the schedule of each of these phases. Brief outages will be needed.
The following is the tentative schedule. Please be advised that this may change as a result of weather or other unforeseen circumstance.
Phase |
Boring - Start Date |
Boring - Estimated Completion |
Conversion - Start Date |
Conversion - Estimated Completion |
1 |
Not Applicable |
Not Applicable |
7/20/2017 |
7/26/2017 |
2 |
7/31/2017 |
8/4/2017 |
8/15/2017 |
8/21/2017 |
3 |
7/24/2017 |
7/28/2017 |
8/3/2017 |
8/4/2017 |
4 |
Not Applicable |
Not Applicable |
8/7/2017 |
8/8/2017 |
5 |
Not Applicable |
Not Applicable |
8/9/2017 |
8/9/2017 |
6 |
Not Applicable |
Not Applicable |
8/22/2017 |
8/28/2017 |
7 |
Not Applicable |
Not Applicable |
8/10/2017 |
8/14/2017 |
8 |
7/17/2017 |
7/21/2017 |
7/27/2017 |
8/2/2017 |