8/14 Update - TCL&P Conversion Project
7/20/2017

8/14/2017 UPDATE:

Highlighted in red are updates to the project schedule. 

Phase Boring - Start Date Boring - Estimated Completion   Conversion - Start Date Conversion - Estimated Completion 
1 Not Applicable Not Applicable 7/20/2017 COMPLETED
2 7/31/2017 8/4/2017 8/15/2017 8/21/2017
3 7/24/2017 7/28/2017 8/2/2017 COMPLETED
4 Not Applicable Not Applicable 8/7/2017 COMPLETED
5 Not Applicable Not Applicable 8/21/2017 8/28/2017
6 Not Applicable Not Applicable 8/8/2017 8/23/2017
7 Not Applicable Not Applicable 8/28/2017 9/11/2017
8 7/17/2017 7/21/2017 7/26/2017 COMPLETED

 

8/1/2017 UPDATE:

Highlighted in red are updates to the project schedule. 

Phase Boring - Start Date Boring - Estimated Completion   Conversion - Start Date Conversion - Estimated Completion 
1 Not Applicable Not Applicable 7/20/2017 COMPLETED
2 7/31/2017 8/4/2017 8/15/2017 8/21/2017
3 7/24/2017 7/28/2017 8/2/2017 8/4/2017
4 Not Applicable Not Applicable 8/7/2017 8/8/2017
5 Not Applicable Not Applicable 8/9/2017 8/9/2017
6 Not Applicable Not Applicable 8/22/2017 8/28/2017
7 Not Applicable Not Applicable 8/10/2017 8/14/2017
8 7/17/2017 7/21/2017 7/26/2017 COMPLETED

 

7/25/2017 UPDATE:

Highlighted in red are updates to the project schedule. 

Phase Boring - Start Date Boring - Estimated Completion   Conversion - Start Date Conversion - Estimated Completion 
1 Not Applicable Not Applicable 7/20/2017 COMPLETED
2 7/31/2017 8/4/2017 8/15/2017 8/21/2017
3 7/24/2017 7/28/2017 8/3/2017 8/4/2017
4 Not Applicable Not Applicable 8/7/2017 8/8/2017
5 Not Applicable Not Applicable 8/9/2017 8/9/2017
6 Not Applicable Not Applicable 8/22/2017 8/28/2017
7 Not Applicable Not Applicable 8/10/2017 8/14/2017
8 7/17/2017 7/21/2017 7/26/2017 8/2/2017

 

Earlier this year, Traverse City Light & Power (TCL&P) approved a meter exchange with Cherryland Electric Cooperative (Cherryland) to transfer customer electric service from Cherryland over to TCL&P and vice versa.  The exchange offered redundancy and increased reliability for both TCL&P and Cherryland customers.

To assist customers impacted by this meter exchange, TCL&P has created maps outlining the location of Cherryland customers who will soon be transferred over to TCL&P service.  

To view the map for phases 1-7, click here.

To view the map for phase 8, click here.

Going forward, TCL&P will provide updates via our website and Facebook Page that will outline the schedule of each of these phases. Brief outages will be needed. 

The following is the tentative schedule. Please be advised that this may change as a result of weather or other unforeseen circumstance.  

Phase Boring - Start Date Boring - Estimated Completion   Conversion - Start Date Conversion - Estimated Completion 
1 Not Applicable Not Applicable 7/20/2017 7/26/2017
2 7/31/2017 8/4/2017 8/15/2017 8/21/2017
3 7/24/2017 7/28/2017 8/3/2017 8/4/2017
4 Not Applicable Not Applicable 8/7/2017 8/8/2017
5 Not Applicable Not Applicable 8/9/2017 8/9/2017
6 Not Applicable Not Applicable 8/22/2017 8/28/2017
7 Not Applicable Not Applicable 8/10/2017 8/14/2017
8 7/17/2017 7/21/2017 7/27/2017 8/2/2017

 

 

 

 